808 Memorial Drive

20210513 (22).jpgsmall 20210603 (20).jpgsmall 202106017 (24).jpgsmall
Lots of action out at 808 Memorial Drive!
 
The unitized scope is nearly complete on all elevations on Building B. The field team is currently closing up the elevations and working on the ground level commercial scope.
 
The crew has also started to shift it into high gear on the final elevation at Dunkin Donuts facing Memorial Drive. The commercial storefronts are in and they have started to hang unitized units as well as prepare to erect the mast climber on the far right side of the elevation.
 
Unitized CW J anchors will be installed this week on Building A, and IMP panel anchors/furring will also start soon.
 
Full project scope includes:
ES Windows Unitized CW System and SEI Unitized Panelwall System
Tecnoglass glazing
Kingspan Designwall2000 horizontal IMP panels
Kingspan Karrier IMP backup wall panels
Vitrobond 4mmFR ACM in 3 custom finishes
Hilti CP 637 Firestopping Mortar
Hilti EOS Quickseal Floorslab fireproofing
Hilti fasteners/anchors
 
Check back for more updates!
 
GC: NEI General Contracting
Architect: Bruner Cott