Progress update from Clippership Wharf! We are about 60% complete with Building 4 – of this four-building development. The team is currently installing AVB, framing, insulation and Trespa panels. We are effectively running five different crews – each completing many different tasks – with the use of four active mast climbers, a boom lift and a scissor lift. Proud of our team and the organization and motivation they have shown on this final building! Both the south and east elevations should be completed by the end of this month; and west and north are due to be completed by mid May. Check back for more updates!

GC: Lendlease

Architect: The Architectural Team, Inc.