Back on site in Somerville!

shs may2020 (1).jpgsma shs may2020 (1).jpgsmall shs may2020 (2).jpgsmall

We are back on site at Somerville High School! The team is ramping up quickly – all while exercising the utmost level of caution during this ongoing pandemic.

We are currently Installing EFCO curtainwall, Oldcastle glazing, NBK Terracotta, Greengirt Framing, Alcotex ACM panels, and Grace VPL 50 AVB.

Also pictured, you will see that Marr Scaffolding Co is installing mast climbers on the North elevation of phase 2. As soon as installation is complete we will be starting to wrap openings with detail membrane and install AVB.

Stay tuned!

GC: Suffolk Construction
Architect: SMMA